Recent and Featured Projects

Interior Repairs to Cecil Field Support Facilities

U-SMC performed extensive electrical and plumbing work for install of DDC controls for 76° return air temperature of hanger and setup install of portable exterior chillers; extracted approximately 600’ x 4 existing undersized conductors from existing raceways in hanger from the HVAC mechanical room to the main distribution panel for hanger; installed from the HVAC mechanical room to the main hanger distribution panel approximately 600’ x 4 of 300 MCM CU, utilizing existing raceways.

Re-fused existing disconnect in the HVAC mechanical room with the proper size fuses and installed new temporary raceway from the HVAC mechanical room to the exterior disconnect. Purchased and erected a 21,400 SF temporary sprung hanger to support navy operations on the flight line.